| DRAWING LIST FOR PRIMARY SUBSTATION WORK | |
| SL. NO. | DRAWING TITLE |
| A | Electrical drawings : |
| 1 | Rusyel Grid station : |
| 1.1 | Key single line diagram of 33kV switchgear showing proposed outgoing feeders |
| 1.2 | Layout - plan & elevation of proposed modifications required for routing and termination of 3x33kV cables at the existing 33kV switchgear |
| 1.3 | Communication system block diagram showing proposed modifications for termination of 3 x FOC cables |
| 1.4 | SCADA system block diagram showing proposed modifications |
| 2 | Rusyel 33/11kV, 3x20MVA Primary Substation : |
| 2.1 | 33/11kV Key single line diagram |
| 2.2 | 33/11kV Protection and metering single line diagram |
| 2.3 | SLD of 415V LV AC switchboard |
| 2.4 | SLD of 110V DC system |
| 2.5 | Site layout plan |
| 2.6 | Equipment and building layout plan & sectional elevations |
| 2.7 | Cable route layout and tray details in cable spreader room |
| 2.8 | Cable route layout and duct bank details in outdoor area |
| 2.9 | SCADA system block diagram |
| 2.10 | Communication system block diagram |
| 2.11 | SCADA I/O list |
| B | Detailed building design : |
| 1 | Architectural layout plan, elevations and details |
| 2 | GA of Foundation, Column, Trenches & RC Details |
| 3 | GA of Plinth Beam Layout and RC Details |
| 4 | First floor Beam layout and RC Details |
| 5 | Roof Beam layout and RC Details |
| 6 | RC Details of floor Slab at first floor |
| 7 | RC Details of Roof Slab at second floor |
| 8 | Layout and RC Details of Lintel Beams, stair case & Miscellaneous Details |
| 9 | Constructional details of septic tank and soak pit |
| 10 | Sanitary and plumbing details |
| 11 | Water supply and distribution schematic |
| 12 | RCC Design calculations for substation building |
| 13 | Design calculation for septic tank and soak pit |
| 14 | Air conditioning system layout and details |
| 15 | Design calculation for Air conditioning system |
| 16 | Design calculation for indoor lighting system |
| 17 | Indoor lighting and small power layout and SLD of substation building |
| 18 | Fire alarm and detection system layout |
| C | Preparation of Tender Specification for Installation of 33/11kV GIS substation of EPIC basis |